The project management team
Whitworth Co Partnership
Tony Redman B Sc FRICS IHBC
**************************
Project discription
"Bardwell is probably one of the most interesting hammer
beam roofs in East Anglia. Hammer beams were very
fashionable at the beginning of the fifteenth century, the finest probably
being the hammer beam roof over Westminster Hall, now part of the Houses
of Parliament.
Bardwell's is dated 1421 on a shield held by an angel attached to a hammer
on the north side. Any hammer beam with a date is rare, and Bardwell's being
a plausibly early date, and also decorated with what we now know to be original
paintwork, with some indication of an early redecoration in the
late fifteenth century.
Unfortunately the beam end bearings have suffered from rot over the years,
and we are now repairing the last two rotten beam ends. This we hope
to achieve without loss of the historic paintwork, which requires ingenuity
on the part of the surveyor and skill on the part of the carpenters who will
be doing the work.
************************
Whitworth Co Partnership architects
and surveyors have been looking after Bardwell church for
half a century, and Tony Redman who now looks after the church feels he
knows almost every joint in the roof! Whitworth Co Partnership have
offices in Bury ST Edmunds, Bishop Stortford, Norwich and an associate office
in York. They are well known for the quality of their work on historic buildings,
as well as conventional architectural work"
|
The specialist contractor
Haymills
(Conservation) Ltd.
of Huntingdon
***************************
Progress Report on Roof Project – Mid
January 2005
1. We are still on target for a finish before Easter.
The planned pattern of work has not been adhered to for various, and good,
reasons, but the overall assessment as of Monday this week was that the planned
finish date would be met.
2. Specific progress is as follows:
a. The South sides of both nave and
chancel roof, with all lead works, are finished. The lead ridge is
not yet installed, and will not be, until both slopes of each roof have been
finished. It is likely that the north slope of the Chancel will be
completed this week when the lead ridge of the chancel will be applied.
Only the gutters and down spouts will then be outstanding on the Chancel
b. On the north side of the Nave roof
there have been several problems with the roof trusses. Repairs to
those at the front and rear of the roof were carried out in the 1990’s, but
these were done from the underside and though they provided a fairly good
short term repair it was obvious upon opening up that additional bracing
to a number of these was required. This has now been applied.
Two of the main trusses in the centre are in a very poor state and have been
found to have little if any sound bearing on the walls. The roof structure
at this point has been supported on the scaffolding and the two ‘hammers’
that support the trusses have been dismantled. The timbers of the trusses
are reasonably sound but the timbers laying on the wall on to which they
had bearing have completely disintegrated.
We have to restore adequate bearings for the trusses and then reassemble
the hammers, all the while trying to preserve the mediaeval painting. This
is proving tricky and time consuming. When it has been completed and
the trusses restored to strength the roof slope can be felted, battened and
slated and the lead work of the gutters and flashings installed. The
timing of this work to the trusses is the element that may delay the completion
c. The cappings of the roof crossing
and the stone cross between the nave and chancel sections of the roof have
been removed and reset.
d. The ladder across the nave roof has
been removed and will be replaced. With the existing access from the
tower this will mean that the roof can be kept clear of leaves (and pigeon
nests) without the need for
The work involved ladders The work on the roof has enabled the
parapet gutters to be widened, making for easier walking and given better
falls, allowing roof water to run off quicker.
f. The contract allowed for up to 6
sq metres of plaster to be renewed. A lot of this work is in progress
in the chancel area. The visual improvement here will be vast.
Throughout all this work we have kept the Church open for Sunday worship
and the regular congregations have enjoyed the added ventilation of enormous
gaps in the roof, acres of plastic sheeting inside and acres outside on the
scaffolding rattling in the wind! We are a hardy lot in Bardwell
***************************
|